The AI-datacenter nuclear buildout
As of 2026-10-16. Companion to spec-ai-nuclear-smr-buildout.json. Supply-side complement to energy-power (which carries the buyer-side PPA summary). Overlay/structural edges only - PPA terms and dollar figures live in notes, so the financial proof core is untouched. Grading is per-claim: fact | interpretation | caveat.
The headline
Every major AI hyperscaler has signed at least one nuclear power agreement for datacenter load. Trackers count roughly 13 announced projects totaling more than 9.8 GW - the largest corporate nuclear-procurement wave on record. Two distinct structures: restart/PPA of existing reactors (nearer-term) and new-build SMRs (2030-2035), with a subset where the hyperscaler also takes equity in the reactor developer.
The deals (fact)
- Microsoft - Constellation (Three Mile Island / Crane): a 20-year, ~$16B PPA to restart TMI Unit 1 (835 MW, rebranded the Crane Clean Energy Center); FERC transmission waiver approved June 1, 2026; first power targeted H2 2027. The most-advanced deal and the first new capacity that will actually serve datacenter load.
- Amazon - X-energy + Talen: Amazon invested ~$700M in X-energy (up to 12 Xe-100 reactors) and bought an AWS campus beside Talen's Susquehanna plant (PA), buying up to 1,920 MW via the grid through 2042 - after FERC rejected the original behind-the-meter interconnection amendment (Nov 2024).
- Google - Kairos Power: a master agreement, 50 MW demo scaling to ~500 MW by 2030 (KP-FHR molten-salt reactors) - the first corporate next-gen-SMR fleet deal.
- Meta (the largest commitment, up to ~6.6 GW): TerraPower Natrium (~8 plants, ~2.8 GW, Gates-backed) + Oklo (~1.2 GW Aurora) + a 20-year PPA for ~1,121 MW from the Clinton plant.
- Oracle: a 1 GW datacenter design powered by 3 SMRs (permits secured).
The vendor-financing loop (interpretation, labeled)
The structural echo of the chip thread: in the equity-stake subset, a hyperscaler funds the reactor builder it will then buy power from. Amazon - X-energy ($700M stake + offtake) is the clearest case; Sam Altman's chairmanship of Oklo (via his AltC SPAC, from which he stepped down in April 2025 to clear a path for potential OpenAI-Oklo dealings) is the governance version - OpenAI's power demand on one side, an Altman-chaired reactor developer on the other. This loop applies to the equity subset, not to the pure PPAs, and intent is not asserted.
The critical caveat (fact)
No datacenter anywhere yet runs on a new reactor built for it. The first new capacity online is the TMI restart in H2 2027; the SMR fleet deals deliver roughly 2030-2035. And SMR economics are unproven at scale: NuScale has the first NRC-certified SMR design, but its flagship UAMPS/Carbon Free Power Project was canceled in 2023 on cost overruns. A further gating constraint is HALEU fuel - the Xe-100 and most advanced SMRs need high-assay low-enriched uranium, a supply bottleneck historically dominated by Russia. So the buildout is, today, overwhelmingly commitments, not delivered power.
How it wires into the map
New supply-side nodes: X_energy, Kairos_Power, Talen_Energy, NuScale (joining existing Oklo, TerraPower, Constellation_Energy, Vistra, Nuclear_SMR, HALEU_Enrichment). Edges run hyperscaler -> developer/utility (the deals), Sam_Altman -> Oklo (the governance tie), X_energy -> HALEU_Enrichment (the fuel bottleneck), NuScale -> Nuclear_SMR (the cautionary cancellation), and Nuclear_SMR -> AI_Datacenters (the thesis, with the not-yet-delivered caveat). All structural overlay.
Cross-references
energy-power (buyer-side PPA table + grid demand) | macro-ai-power-grid-bottleneck (the grid-interconnection wall) | spec-datacenter-ratepayer-costshift (the Susquehanna FERC fight and ratepayer cost-allocation) | fin-nvidia-openai (the chip vendor-financing loop this mirrors on the power side) | spec-oracle-ai-credit-lynchpin (Oracle's 1 GW / 3-SMR design in the credit context).